LNG Steam Simulator Exercise
019. Run the Simulator to Change over to Scoop Sea-water Circulation<
[Load Snapshot "Ex_009_Changing Over from DO to HFO_Burning"]
- Asssume scenario as described below [but check to confirm] and then follow the given procedures
Electrical Power:-
Shore Power:Off; Emergency Generator:Auto Stand-by; Turbo Generators:One on load and the other off; Diesel Generator:On Load
Deaerator:-
Full with guage glass reading between 60~70 mm
Both Boilers:-
Both Boiler Press - aboout 6 Mpa; Both boilers are running on HFO supply.
Condenser:-
Condenser Vacuum is Satisfactory and Cooling on
Distilled Water Tank (DWT) & Atmospheric Drain Tank (ADT):-
Both DWT & ADT about 60% full.
>> Procedure to prepare Main Sea Water Cooling (Ship Speed More than 8 Knots):-
Main Condenser:
1 Open the Scoop by clicking on the button.
2 Ensure the Main Circ. Overboard valve is open.
3 Stop SW Main Circ pump(s).
4 Put a SW MAin Circ. Pump into standby and keep valves open.
NOTE:
1) Check Knowledgebase - .........